Dec 7, 20235 min read
Scope of the Grove Principle - Can I Commence Adjudication Proceedings Before Paying a Notified Sum?
Key Points In S&T(UK) Ltd v Grove[1], it was held that a payer (with respect to a construction contract) must comply with its immediate...


Nov 15, 20236 min read
Hybrid Payment Notices and Invoice-Linked Payment Dates are Non-compliant with the Construction Act
The TCC held that linking the final date for payment to service of a VAT invoice was non-compliant with the Construction Act.


Sep 24, 20205 min read
Who Owns the Materials?
If you supply materials on a construction project and the main contractor becomes insolvent before you receive payment, a number of factors


Sep 3, 20202 min read
Does Your Subcontract Allow You To Terminate if the Main Contractor Becomes Insolvent?
Does your subcontract allow you to terminate if the main contractor becomes insolvent? Following implementation of new legislation, it...


Aug 27, 20205 min read
Is Your Final Date For Payment Linked To Service of a VAT Invoice?
Recent comments by the TCC cast doubt on the practice of linking the final date for payment to issue of a VAT invoice